Scrum has five events: the sprint itself, which contains sprint planning, the daily scrum, the sprint review and the sprint retrospective. Sprint planning needs the most structure on paper, because it should end with a sprint goal, the backlog items the developers select for the sprint, and their plan for delivering them. This template records capacity, the goal, the selected items, risks and what was left out.
Looking for the 15-minute daily scrum? Use the daily standup template. This page is for sprint planning.
Goal met or not. Completed points or items. What carried over and where the product owner ranked it.
| Person | Days available | Note |
|---|---|---|
| Leave, on-call, holidays |
Total person-days, and what the team completed last sprint
One or two sentences: why this sprint is worth doing
| ID | Item | Estimate | Starts with | Still unclear |
|---|---|---|---|---|
| Question, and who answers it |
| Risk or dependency | Owner | Next step |
|---|---|---|
| Item | Owner | Due |
|---|---|---|
| Item | Owner | Time | What we need to leave with |
|---|---|---|---|
| Last sprint result and carry-over | Scrum master | 10 min | Carry-over items back in the product backlog, re-ranked |
| Capacity for this sprint | Developers | 10 min | Agreed person-days available |
| Why: proposed sprint goal | Product owner, then the whole scrum team | 15 min | A sprint goal the whole team agrees on |
| What: select backlog items | Developers with the product owner | 40 min | Items pulled in, each estimated and clear enough to start |
| How: plan the delivery, first items in detail | Developers | 30 min | A plan the developers own, with work for the first days broken down |
| Confirm goal, risks and read-back | Scrum master | 10 min | Final sprint goal, each risk with an owner |
| Event | When | Timebox (Scrum Guide, for a one-month sprint) | What it produces |
|---|---|---|---|
| Daily scrum | Every working day, same time and place | 15 minutes, whatever the sprint length | A plan for the next day, blockers raised |
| Sprint review | End of the sprint | At most 4 hours, usually shorter for shorter sprints | Feedback from stakeholders, an updated product backlog |
| Sprint retrospective | After the review, before the next planning | At most 3 hours, usually shorter for shorter sprints | One or two improvements for the next sprint |
| Backlog refinement | Ongoing, often one session mid-sprint | No set length (an activity, not a scrum event) | Items ready for the next sprint planning |
Sprint 13 goal (freelancers can send invoice reminders automatically) was met. 21 of 23 points done. QF-212, the Spanish reminder email copy, carried over. Ana ranked it third in the product backlog.
| Person | Days available | Note |
|---|---|---|
| Ines | 8 | Office closed Nov 26 and 27 |
| Ray | 6 | Also off Nov 19 and 20 |
| Mei | 8 | |
| Tobi | 7 | On call Nov 16 to 20, counting one day lost |
| Carla | 8 |
Total 37 person-days. Sprint 13 had 46 person-days and finished 21 points, so roughly 17 points is realistic this time.
Freelancers can take a card payment on an invoice and see it marked paid without refreshing the page.
| ID | Item | Estimate | Starts with | Still unclear |
|---|---|---|---|---|
| QF-230 | Pay by card button on the invoice page | 5 | Mei | Which card brands at launch? Ana to confirm. |
| QF-231 | Payment webhook marks the invoice paid | 5 | Ray | |
| QF-235 | Payment receipt email | 3 | Ines | |
| QF-238 | Paid status updates live on the invoice list | 3 | Tobi | Polling or push? Spike Tuesday morning. |
| QF-212 | Spanish reminder email copy (carried over) | 2 | Carla | Translation due from the agency Nov 18 |
| Risk or dependency | Owner | Next step |
|---|---|---|
| Payment provider hasn't approved the live account yet | Ana | Contact provider support Monday afternoon. If not approved by Nov 18, the goal changes to test mode only. |
| 18 points selected against a realistic 17 in a short sprint | Jonah | QF-212 is the first item to drop if needed |
| Translation arrives late | Carla | Ask the agency for a firm delivery date |
| Item | Owner | Due |
|---|---|---|
| Confirm card brands for launch | Ana | Nov 17 |
| Get a delivery date from the translation agency | Carla | Nov 17 |
| Add QF-240 to the Nov 19 refinement session | Jonah | Nov 18 |