A retrospective or post mortem looks back at a sprint, project or incident and ends with a short list of changes, each with one owner. The notes should check whether last time's actions were done, lay out a timeline of what happened, list what went well and what didn't, name the causes the team can act on, and record two or three actions with dates.
Best forAgile teams after each sprint, and any team after a project, launch or incident
Meeting length45 to 60 minutes for a sprint, 60 to 90 minutes for a project post mortem
SectionsLast actions, timeline, what went well, what didn't go well, why it happened, actions
ReviewingSprint, project or incidentDateTime60 minFacilitatorSomeone not deeply involved in the work, if possibleNotes by
Item
Owner
Time
What we need to leave with
Ground rule and purpose
Facilitator
3 min
Everyone has heard the no-blame rule
Actions from last retro
Facilitator
5 min
Each action marked done, in progress or dropped
Timeline of what happened
Project lead
10 min
An agreed order of events with dates
What went well and what didn't (silent writing)
Everyone
10 min
Input from every person, not just the loudest
Group and vote
Facilitator
7 min
The top 2 or 3 problems to dig into
Why it happened
Everyone
15 min
A cause the team can act on for each top problem
Actions and read-back
Notes taker
10 min
2 or 3 actions, each with one owner and a date
Word MarkdownPastes into Google Docs, Word or Notion with headings and tables intact. Copied. Paste it into your document.
Cedar & Salt online ordering launch, post mortem
Filled-in example
Cedar & Salt online ordering launch, post mortem
ReviewingOnline ordering launch at three restaurant locationsPeriodAugust 24 to October 23, 2026DateWednesday, October 28, 2026, 3:00 to 4:05 pmAttendeesJess Albright (operations manager, project lead), Kofi Mensah (IT contractor), Laura Pineda (marketing), Tim Holloway (general manager, Elm Street)FacilitatorRavi Shah (finance, not on the project team)Notes byLaura Pineda
Actions from last retro
Action
Owner
Status
Get menu sign-off from all three head chefs before anything is published (spring menu refresh)
Jess
Done. Used again for the online menu.
Keep one shared launch checklist instead of email threads
Laura
Dropped. Never set up, and it came up again today.
Timeline
Date
What happened
Aug 24
Project approved. Launch set for Oct 1 to match the fall menu campaign.
Sep 8
Ordering platform contract signed, two weeks later than planned
Sep 28
Test orders: the kitchen printer at Elm Street doesn't print online orders
Sep 29
Last location's menu photos and item details delivered (due Sep 21)
Sep 30
Launch moved to Oct 15. Customers emailed the new date.
Oct 9
Printer vendor updates the Elm Street printer
Oct 13 and 14
Kitchen and front-of-house training at all three locations
Oct 15
Launch at all three locations
Oct 16
Friday dinner at Elm Street: 11 online orders ready late, two refunded
What went well
Every shift was trained before launch. No order-handling mistakes in the first week.
Kofi's test order plan caught the printer problem before any customer did.
The new launch date email went out the same day the date moved. 140 online orders in week one.
What didn't go well
Problem
Votes
Launch date announced before the platform contract was signed
4
Printer compatibility only checked in test week
3
Elm Street Friday rush: online orders competing with dine-in tickets
3
Menu details arrived late from one location
1
No shared checklist, status lived in Jess's inbox
1
Why it happened
Problem
Cause
In our control?
Launch date before contract
The date came from the marketing calendar, not a delivery plan
Yes
Printer found late
Nobody owned hardware. The platform's setup checklist assumed newer printers.
Yes
Elm Street Friday rush
The limit on online orders per 15 minutes was off by default. Staffing may also be a factor.
Partly. Tim wants two more Fridays of data before deciding on staffing.
Actions
ID
Action
Owner
Due
How we'll know it worked
R1
Add a contract-signed check and a two-week buffer to the project approval form
Jess
Nov 6
Updated form used for the catering portal project
R2
Make hardware compatibility a named task with an owner in every IT project plan
Kofi
Nov 13
Line added to the project plan template
R3
Turn on the online order limit at Elm Street for Friday and Saturday dinner
Tim
Oct 30
Setting on, late orders checked after Oct 30 and Nov 6
R4
Decide who owns a shared launch checklist
Jess (to raise at the Nov 4 ops meeting)
Nov 4
A named owner. Still unassigned after two retros.
Cedar & Salt and everyone named here are a fictional sample.
Best forAgile teams after each sprint, and any team after a project, launch or incident
Meeting length45 to 60 minutes for a sprint, 60 to 90 minutes for a project post mortem
SectionsLast actions, timeline, what went well, what didn't go well, why it happened, actions
FormatsGoogle Docs, Word, Notion, Markdown
When to use this template
Your retros produce the same complaints every two weeks and nothing changes.
A project or launch went badly and you need to review it without it turning into blame.
A project went well and you want to know why, so the next one runs the same way.
Questions people ask
What is the difference between a retrospective and a post mortem?
A retrospective is a regular review, usually at the end of every sprint (before the next sprint planning), about how the team works. A post mortem looks at one finished project, launch or incident, so it spends more time on the timeline. This template works for both: skip the timeline for a routine sprint retro.
Who should facilitate a post mortem meeting?
Someone who wasn't deeply involved, so they can ask plain questions and keep it from becoming a defense of decisions. The project lead should attend and walk through the timeline, but not run the meeting.
How do you stop retros from repeating the same problems?
Start every retro with last time's actions and cap new actions at two or three. If a problem keeps coming back, the fix usually sits outside the team, so name the person who can change it and take it to them.