Weekly construction (OAC) meeting

Construction meeting minutes template

Construction meeting minutes record the weekly owner, architect and contractor (OAC) meeting: safety, progress against the schedule and look-ahead, open RFIs and submittals, pending changes, inspections and site coordination. Every open issue gets a number and stays in the log, with who is responsible, until it is closed. Send the minutes within a day or two and ask for corrections by a date; what an uncorrected set of minutes counts for is up to your contract.

Best forGeneral contractors, project managers, owner's reps and architects on active projects
Meeting length45 to 90 minutes, weekly
SectionsAttendance by company, safety, schedule and look-ahead, RFIs, submittals, changes, inspections, site coordination, open items log
FormatsGoogle Docs, Word, Notion, Markdown
Word Markdown
[Project] weekly construction meeting minutes, meeting no. [ ].docx
[Project] weekly construction meeting minutes, meeting no. [ ]
Date and time Location Prepared by Distribution 

Attendance

NameCompanyRole
 Owner / Architect / Contractor / Sub 

Safety

  • Incidents or near misses since last meeting
  • Open safety items on site
  • Toolbox talk topic this week

Schedule and three-week look-ahead

Status against baseline and substantial completion date: Slipped activities, cause and recovery plan:

Week ofPlanned workInspections or milestones
   

RFIs

No.SubjectSentAnswer dueBall in courtStatus
     Open / Answered / Closed

Submittals

No.ItemSubmittedStatusLead time or note
   Under review / Approved / Approved as noted / Revise and resubmit / Not yet submitted 

Changes

No.DescriptionAmountStatus
PCO or CO number  Pricing / Under review / Approved / Executed / Disputed

Quality, inspections and site coordination

  • Inspections passed, failed or requested
  • Shutdowns, deliveries, access and neighbor issues

Open items log

ItemDescription and latest noteResponsibleDueStatus
Meeting.line, e.g. 12.03   Open / Closed

Next meeting

Date, time, location.

Corrections

These minutes are the preparer's understanding of the meeting. Send corrections to [name] by [date]. Sent to: [names], on [date]. How long people have to object, and what uncorrected minutes count for, follow the contract: [clause, or "not addressed"].

Word MarkdownPastes into Google Docs, Word or Notion with headings and tables intact.
Best forGeneral contractors, project managers, owner's reps and architects on active projects
Meeting length45 to 90 minutes, weekly
SectionsAttendance by company, safety, schedule and look-ahead, RFIs, submittals, changes, inspections, site coordination, open items log
FormatsGoogle Docs, Word, Notion, Markdown

When to use this template

Questions people ask

Who takes the minutes in a weekly construction meeting?
Usually the general contractor's project manager, sometimes the architect or the owner's rep. Check the contract, which often says who prepares and distributes them. Whoever does it should send them quickly, because minutes sent two weeks late are hard to correct.
What does ball in court mean in construction minutes?
It names the party who has to act next on an RFI, submittal or change. Writing it on every open item makes delays visible: when an RFI is overdue, everyone can see whether the architect, the owner or the contractor is holding it.
Why number open items by meeting, like 13.02?
The number tells you when the issue was first raised and never changes as it carries forward. Months later, "item 11.04 has been open since meeting 11" is a clear fact, and it is easy to search across a stack of minutes.